Former Nailstone Colliery – Pumping Station
Project Details
- Location: Nailstone
- Client: Curtis Hall
- End User: Aldi
- Value: £0.30 million
- Architect: Stephen George & Partners
- Engineer: Bradbrook Consulting
- Programme: 5 weeks
Share Project:
BlueEarth Construction have been appointed by Curtis Hall to complete install the adoptable pumping station at the Former Nailstone Colliery.
The main contract works included;
- Earthworks / Ground Preparation
- Chambers / Aquaspira
- Pumping Station
- Concrete Hard Standing
- Fencing
Project images:
All images owned and copyright by BlueEarth Construction ©