Littlebrook power station (the Powerhouse), Dartford – phase 3 (outfall & forebay shaft)

Project Details

Share Project:

BlueEarth Construction was appointed by Bericote Properties to complete the capping of the outfall and forebay shafts circa 45m below sea level at the Littlebrook Power Station (The PowerHouse) in Dartford.

The main contract works included;

  • Screen and deposit 6A & 6F2 material into shafts
  • Monitor the fill level for 12 week
  • Pump out shafts
  • Construct concrete cap

Project images:

All images owned and copyright by BlueEarth Construction  ©

More Projects...

Blue Earth Construction Main contractor delivering enabling works at Wood Farm Bardon industrial development site

Wood Farm Bardon 3 – Enabling Infrastructure for Industrial Development

Modern industrial unit with integrated office space at Birmingham Business Park, featuring pedestrian access, parking, and landscaped surroundings.

Project Diamond – Industrial Development at Birmingham Business Park

BlueEarth Construction - Main Contractor - Place Holder

Richard Lester – Retaining Walls

Scroll to Top