BlueEarth Construction was appointed by Bericote Properties to complete the capping of the outfall and forebay shafts circa 45m below sea level at the Littlebrook Power Station (The PowerHouse) in Dartford.

The main contract works included;

  • Screen and deposit 6A & 6F2 material into shafts
  • Monitor the fill level for 12 week
  • Pump out shafts
  • Construct concrete cap