IAE – Project Update

A fantastic start for BlueEarth Construction on the manufacturing facility for IAE

Base Build works are well underway and progressing at pace. Works are on course to be complete by 03rd December 2021

BlueEarth are extremely pleased to be exceeding the client’s expectations in partnership with our trusted supply chain;

  • Steel Pile Foundations – Van Elle – Complete
  • Vibro Ground Improvement – Vibro Menard – Complete
  • Pile Caps – ANC Staffs – Complete
  • External Concrete Hardstanding – Fortel – 90% Complete
  • Steel Frame – Severfield – 30% Complete
  • Siphonic Roof Drainage – Sapoflow – Start on Site Monday 23rd August 2021
  • Roofing and Cladding – Yorkshire Sheeting – Start on Site Monday 23rd August 2021

IAE – Project Update

Share:

Twitter
LinkedIn
Email
WhatsApp

In other news...

Modern industrial unit with integrated office space at Birmingham Business Park, featuring pedestrian access, parking, and landscaped surroundings.

Project Diamond

Blue Earth Construction work on Phase 1A Bardon 3 - Design & Construction, Leicestershire - ariel view

Phase 1A – Bardon

BlueEarth Construction to Use Asite Across Project Portfolio

New timelapse now live of Aero Fabrications

Phase II Extension to Aero Fabrications, Nottingham

Hartshorne Motor Services, Walsall

Project Update – IAE Stoke

Ducati Tri-Options Championship – Its All Over!

John McGuinness – Return to the Podium

IAE – Project Update

Scroll to Top