IAE – Project Update

A fantastic start for BlueEarth Construction on the manufacturing facility for IAE

Base Build works are well underway and progressing at pace. Works are on course to be complete by 03rd December 2021

BlueEarth are extremely pleased to be exceeding the client’s expectations in partnership with our trusted supply chain;

  • Steel Pile Foundations – Van Elle – Complete
  • Vibro Ground Improvement – Vibro Menard – Complete
  • Pile Caps – ANC Staffs – Complete
  • External Concrete Hardstanding – Fortel – 90% Complete
  • Steel Frame – Severfield – 30% Complete
  • Siphonic Roof Drainage – Sapoflow – Start on Site Monday 23rd August 2021
  • Roofing and Cladding – Yorkshire Sheeting – Start on Site Monday 23rd August 2021